Training for BOP Technologies (Example)
2. Training Program
Classroom Training (CRT)
1) Common Training
Discipline |
Subject |
Hours |
Remarks |
General |
1) Orientation & Project Management |
2 |
|
2) Project Schedule Control Management |
2 |
|
3) Project Cost Control Management |
2 |
|
4) Quality Control Management |
2 |
|
Nuclear |
5) Overview of Nuclear Power Plant |
2 |
|
6) Licensing of Nuclear Power Plant |
2 |
|
7) Reliability Analysis |
2 |
|
8) NSSS & Safety Related System |
2 |
|
9) Safety Analysis |
2 |
|
10) Radiographic Protection |
2 |
|
11) Radioactive Waste Disposal System |
2 |
|
12) Layout Plan of Nuclear Power Plant |
2 |
|
13) Mechanical System of Nuclear Power Plant |
2 |
|
14) System overview of BOP |
2 |
|
15) HVAC of Nuclear Power Plant |
2 |
|
16) Electrical Power System in Power Plant |
2 |
|
17) Outside Transformation System of Electric Energy |
2 |
|
18) General of NPP Structure |
2 |
|
19) C.A.S Engineering of RCB |
2 |
|
20) Environment Licensing of Nuclear Power Plant |
2 |
|
21) Commissioning |
2 |
|
22) Environmental Qualification |
2 |
|
Total |
|
44 |
|
2) In-Depth Training
Discipline |
Subject |
Hours |
Remarks |
Civil |
1) Introduction of Civil Design for NPP |
2 |
|
2) Auxiliary Building(AB) Design |
2 |
|
3) Turbine Generator Building(TGB) Design |
2 |
|
4) Special Structural Analysis |
2 |
|
5) Yard Facilities Structures |
2 |
|
6) General Design Criteria |
2 |
|
7) Hydrologic Engineering |
2 |
|
8) Seismic Analysis |
2 |
|
9) Aircraft Impact Analysis |
2 |
|
10) RCB Basemat Design |
2 |
|
11) Shell & Dome Design |
2 |
|
12) RCB Internal Structure Design |
2 |
|
13) Steel Structure Design |
2 |
|
14) Composite Frame Design |
2 |
|
15) Shear Wall Design |
2 |
|
16) Nuclear Steam Supply System Support & Pipe Support Design |
2 |
|
17) Geology and Geotechnical Engineering |
2 |
|
18) Intake & Discharge Structure Design |
2 |
|
Total |
|
36 |
|
Discipline |
Subject |
Hours |
Remarks |
Electrical |
1) Introduction of Electrical Design for NPP |
2 |
|
2) Overview of Electrical System |
2 |
|
3) Switchyard System |
2 |
|
4) Separation Criteria |
2 |
|
5) Relaying System |
2 |
|
6) Power Transformer |
2 |
|
7) EDG |
2 |
|
8) Introduction for Electrical Facility |
2 |
|
9) DC/IP System |
2 |
|
10) Switchgear (SWGR) |
2 |
|
11) Circuit Breaker |
2 |
|
12) AC Power System |
2 |
|
13) Cable |
2 |
|
14) Motor Control Center (MCC) |
2 |
|
15) Load Center (LC) |
2 |
|
16) Short Circuit Calculation and Voltage Drop |
2 |
|
17) Fire Detection |
2 |
|
18) Electrical System Grounding |
2 |
|
Total |
|
36 |
|
Discipline |
Subject |
Hours |
Remarks |
I&C |
1) Introduction of I/C Design for NPP |
2 |
|
2) Instruction of Human Factors Engineering System |
2 |
|
3) MMIS Codes & Standards |
2 |
|
4) Instruction of MMI (including Alarm) |
2 |
|
5) Technical Evaluation of Proposals |
2 |
|
6) Instruction of Radiation Monitoring System |
2 |
|
7) Design of IID for Instruments |
2 |
|
8) Instrument Numbering Guideline |
2 |
|
9) Instruction of Man-Machine Interface System |
2 |
|
10) Instruction of the C&ID & CLD System and Legend |
2 |
|
11) Design of ILD |
2 |
|
12) Instruction for Control Room HVAC System (Including P&ID, C&ID/CLD and etc.) |
2 |
|
13) Instruction for Process Sampling System (Including P&ID, C&ID/CLD and etc.) |
2 |
|
14) Instruction for Containment Monitoring System (Including P&ID, C&ID/CLD and etc.) |
2 |
|
15) Instruction for Main Steam System (Including P&ID, C&ID/CLD and etc.) |
2 |
|
16) Instruction & Purchase Specification of Control Valves |
2 |
|
17) Instruction for Feed Water System (Including P&ID, C&ID/CLD and etc.) |
2 |
|
18) Instruction for Component Cooling Water System (Including P&ID, C&ID/CLD and etc.) |
2 |
|
Total |
|
36 |
|
Discipline |
Subject |
Hours |
Remarks |
Mech./Nuclear |
1) Introduction of Mechanical/Nuclear Design for NPP |
2 |
|
2) Overall Cooling Water System |
2 |
|
3) Steam Turbine & Auxiliary System |
2 |
|
4) Feedwater System |
2 |
|
5) Pump, Pipe Sizing & Pressure Drop |
2 |
|
6) Control room HVAC System |
2 |
|
7) IRWST System |
2 |
|
8) Spent Fuel Pool Cooling System Design |
2 |
|
9) Component Cooling Water System Design |
2 |
|
10) Essential Water Service System Design, Primary Sampling System Design |
2 |
|
11) Steam Generator Blowdown System Design |
2 |
|
12) Gaseous Radwaste System Design, Liquid Radwaste System Design |
2 |
|
13) Circulating water system |
2 |
|
14) Condensate System |
2 |
|
15) Plant Chilled Water System |
2 |
|
16) Fire Protection System |
2 |
|
17) Water Treatment System |
2 |
|
18) Containment Spray System |
2 |
|
Total |
|
36 |
|
On-the-Job Training (OJT)
Discipline |
Subject |
Hours |
Remarks |
Civil |
1) Procedure of Civil Engineering |
3 |
|
2) Auxiliary Building(AB) Design |
3 |
|
3) Turbine Generator Building(TGB) Design |
3 |
|
4) Special Structural Analysis |
3 |
|
5) Yard Facilities Structures |
3 |
|
6) General Design Criteria |
3 |
|
7) Hydrologic Engineering |
3 |
|
8) Seismic Analysis |
3 |
|
9) Aircraft Impact Analysis |
3 |
|
10) RCB Basemat Design |
3 |
|
11) Shell & Dome Design |
3 |
|
12) RCB Internal Structure Design |
3 |
|
13) Steel Structure Design |
3 |
|
14) Composite Frame Design |
3 |
|
15) Shear Wall Design |
3 |
|
16) Nuclear Steam Supply System Support & Pipe Support Design |
3 |
|
17) Geology and Geotechnical Engineering |
3 |
|
18) Intake & Discharge Structure Design |
3 |
|
19) Intensive OJT |
38 |
|
Total |
|
92 |
|
Discipline |
Subject |
Hours |
Remarks |
Electrical |
1) Procedure of Electrical Engineering |
3 |
|
2) Overview of Electrical System |
3 |
|
3) Switchyard System |
3 |
|
4) Separation Criteria |
3 |
|
5) Relaying System |
3 |
|
6) Power Transformer |
3 |
|
7) EDG |
3 |
|
8) Introduction for Electrical Facility |
3 |
|
9) DC/IP System |
3 |
|
10) Switchgear (SWGR) |
3 |
|
11) Circuit Breaker |
3 |
|
12) AC Power System |
3 |
|
13) Cable |
3 |
|
14) Motor Control Center (MCC) |
3 |
|
15) Load Center (LC) |
3 |
|
16) Short Circuit Calculation and Voltage Drop |
3 |
|
17) Fire Detection |
3 |
|
18) Electrical System Grounding |
3 |
|
19) Intensive OJT |
38 |
|
Total |
|
92 |
|
Discipline |
Subject |
Hours |
Remarks |
I&C |
1) Procedure of I/C Engineering |
3 |
|
2) Instruction of Human Factors Engineering System |
3 |
|
3) MMIS Codes & Standards |
3 |
|
4) Instruction of MMI (including Alarm) |
3 |
|
5) Technical Evaluation of Proposals |
3 |
|
6) Instruction of Radiation Monitoring System |
3 |
|
7) Design of IID for Instruments |
3 |
|
8) Instrument Numbering Guideline |
3 |
|
9) Instruction of Man-Machine Interface System |
3 |
|
10) Instruction of the C&ID & CLD System and Legend |
3 |
|
11) Design of ILD |
3 |
|
12) Instruction for Control Room HVAC System (Including P&ID, C&ID/CLD and etc.) |
3 |
|
13) Instruction for Process Sampling System (Including P&ID, C&ID/CLD and etc.) |
3 |
|
14) Instruction for Containment Monitoring System (Including P&ID, C&ID/CLD and etc.) |
3 |
|
15) Instruction for Main Steam System (Including P&ID, C&ID/CLD and etc.) |
3 |
|
16) Instruction & Purchase Specification of Control Valves |
3 |
|
17) Instruction for Feed Water System (Including P&ID, C&ID/CLD and etc.) |
3 |
|
18) Instruction for Component Cooling Water System (Including P&ID, C&ID/CLD and etc.) |
3 |
|
19) Intensive OJT |
38 |
|
Total |
|
92 |
|
Discipline |
Subject |
Hours |
Remarks |
Mech./Nuclear |
1) Procedure of Mechanical/Nuclear Engineering |
3 |
|
2) Overall Cooling Water System |
3 |
|
3) Steam Turbine & Auxiliary System |
3 |
|
4) Feedwater System |
3 |
|
5) Pump, Pipe Sizing & Pressure Drop |
3 |
|
6) Control room HVAC System |
3 |
|
7) IRWST System |
3 |
|
8) Spent Fuel Pool Cooling System Design |
3 |
|
9) Component Cooling Water System Design |
3 |
|
10) Essential Water Service System Design, Primary Sampling System Design |
3 |
|
11) Steam Generator Blowdown System Design |
3 |
|
12) Gaseous Radwaste System Design, Liquid Radwaste System Design |
3 |
|
13) Circulating water system |
3 |
|
14) Condensate System |
3 |
|
15) Plant Chilled Water System |
3 |
|
16) Fire Protection System |
3 |
|
17) Water Treatment System |
3 |
|
18) Containment Spray System |
3 |
|
19) Intensive OJT |
38 |
|
Total |
|
92 |
|